We honestly couldn’t recommend Shane highly enough. From the very beginning, Shane guided us through every step of the process with...
Read full reviewKnockdown rebuild finance in NSW: what lenders need before they approve
A knockdown rebuild is financed as a construction loan secured against the land. The lender values the property on an as-if-complete basis, using the stamped plans and a fixed price building contract, while the old house is still standing. Approval needs council or private certifier approval, a fixed price contract, home warranty insurance and a full specification. In NSW, a complying development certificate is usually the faster approval path where the design fits the standard controls.
Knockdown rebuilds are more common in Western Sydney than anywhere else in the state, because the land is worth keeping and the houses on it often are not. The finance is straightforward once you understand what the lender is actually valuing.
How the valuation works
This is the part that confuses people. You are asking a lender to lend against a house that does not exist yet, on land currently occupied by a house you are about to destroy.
The valuer is instructed on an as-if-complete basis. They take the stamped plans, the specification and the fixed price contract, and they assess what the finished property will be worth on that land at completion. The existing dwelling is essentially ignored, other than as a cost to remove.
| Item | Amount | Notes |
|---|---|---|
| Land value (existing property) | $850,000 | Current value with the old dwelling |
| Existing mortgage | $300,000 | Refinanced into the construction facility |
| Demolition | $35,000 | Often funded outside the construction contract |
| Fixed price build contract | $720,000 | Drawn in stages |
| As-if-complete valuation | $1,650,000 | Land plus completed dwelling |
| Total borrowing required | $1,055,000 | Existing debt plus demolition plus build |
| Resulting LVR on completion | 64% | Comfortably inside standard policy |
Illustrative only. Your own land value, contract price and valuation will differ. This is not a quote or an indication of approval.
Note what makes this work: the as-if-complete valuation is well above the total borrowing, so the LVR at completion is modest even though the borrower is funding almost the whole build. That is the normal shape of a well-planned rebuild, and it is why lenders are comfortable with them.
CDC or DA: the approval path
NSW gives you two routes to approval, and the choice affects your timeline more than your finance.
| Complying development certificate (CDC) | Development application (DA) | |
|---|---|---|
| Issued by | A private certifier or council | Council |
| Typical timeframe | 2 to 6 weeks | 3 to 9 months, sometimes longer |
| Requires | Design fits within the standard codes: setbacks, height, floor space ratio, landscaping, lot size | Anything outside the codes, or a lot with constraints |
| Neighbour notification | Notification only, no objection process | Public exhibition and objections |
| Lender treatment | Accepted as approval | Accepted as approval |
| Common blockers | Heritage, flood, bushfire, acid sulfate soils, foreshore, narrow or battleaxe lots | Fewer hard blockers, but slower |
Most standard rebuilds in Blacktown, Penrith, Parramatta and the Hills go the CDC route where the block allows it. Where the block is flood affected, heritage listed or unusually shaped, a DA is the only option and the timeline stretches accordingly. That timeline matters for finance because approvals expire, and so do loan approvals.
What lenders want to see
- Approval documents. The stamped CDC or DA plans, matching the contract.
- A fixed price building contract. Cost plus contracts are hard to finance and some lenders will not consider them at all.
- Home warranty insurance for the contract value, in your name, issued before the first drawdown.
- The full specification and inclusions schedule. The valuer values the specification, so vagueness costs you.
- Builder licence details and evidence the builder is currently licensed for the work.
- BASIX certificate for the new dwelling.
- Demolition arrangements, including how demolition is being paid for and whether an asbestos report has been done.
- Evidence of where you will live during the build, because the lender will assess rent alongside your loan repayments.
Demolition: the gap most people miss
Demolition sits awkwardly between the old loan and the new one. In Sydney, a standard single storey demolition runs roughly $25,000 to $45,000, and asbestos removal pushes it higher. Houses built before the late 1980s frequently have asbestos in the eaves, the bathroom sheeting or the fence.
Where demolition is inside the builder's fixed price contract, it is funded as part of the first drawdown and everything is simple. Where it is a separate contract, which is common, many lenders will not fund it from the construction facility. That means either cash, or an equity release against the existing property completed before the build facility starts.
Getting this sequenced right is worth doing early, because a demolition that has already happened changes the security position and can complicate the valuation.
The timeline to plan against
- 1Months 1 to 3
Design and approval
Draftsperson or architect, then CDC through a private certifier, or a DA lodged with council. This is the stage most likely to blow out.
- 2Months 2 to 4
Builder selection and fixed price contract
Tender the plans, compare inclusions rather than headline prices, and sign a fixed price contract.
- 3Weeks 1 to 4 of finance
Loan application and as-if-complete valuation
Submission, valuation on the plans and contract, then formal approval.
- 4Weeks 4 to 6
Settlement of the facility and move out
The existing loan is refinanced into the construction facility, and you move into rental accommodation.
- 5Weeks 6 to 10
Demolition and site preparation
Service disconnections, asbestos clearance where required, demolition, site clear.
- 6Months 4 to 14
Construction in progressive drawdowns
Slab, frame, lock-up, fit-out, completion. Repayments climb as each stage is drawn.
- 7Month 14 to 18
Practical completion and handover
Final inspection, final drawdown, occupation certificate, and the loan converts to principal and interest.
Twelve to eighteen months from first drawing to handover is realistic for a standard rebuild. The finance is usually the shortest part of it.
The cost people forget
You are paying rent and loan interest at the same time for the whole build. On the worked example above, interest through the build averages around $4,000 a month, and Western Sydney rent for a family home is $650 to $850 a week. That combined cost across fourteen months is a real number and it belongs in the budget from day one, not month six.
The site costs that blow rebuild budgets
The build contract is the number everyone focuses on. The site costs are the number that moves. On an established block, the ground under the old house has been there for sixty years and nobody has looked at it.
| Item | Indicative cost | When you find out |
|---|---|---|
| Asbestos removal | $5,000 to $25,000 | Pre-demolition survey |
| Reactive clay soil, deeper footings | $10,000 to $40,000 | Soil test, before contract if you order it early |
| Retaining walls on a sloping block | $15,000 to $60,000 | Detailed survey and design |
| Sydney Water sewer main under the block | $8,000 to $50,000 | Sewer diagram, obtain it before you buy or design |
| Service disconnections and reconnections | $3,000 to $12,000 | Demolition stage |
| Tree removal and protection orders | $2,000 to $15,000 | Council arborist assessment |
Indicative Sydney ranges at September 2026. Costs vary by block, council and contractor.
Two documents remove most of this uncertainty and both can be obtained before you commit: a sewer diagram from Sydney Water, and a soil classification report. Together they cost a few hundred dollars and routinely change the design, the build price, or the decision to proceed at all.
From a finance perspective, the risk is that site costs emerge after the loan is approved against the original contract sum. The lender approved $720,000 of building work, the build is now $770,000, and the extra has to come from somewhere. A contingency of five to ten percent held in cash outside the contract is the simplest protection, and it is the thing most rebuild budgets leave out.
We build that figure into the servicing assessment before anything goes to a lender, because a rebuild that services on paper but not in practice is nobody's idea of a good outcome. Our construction loans page covers the drawdown process in detail, or book a free call and we will map your block against a realistic funding plan.
Frequently asked questions
Want this looked at for your situation?
Book a free call. No fee in most cases, and no obligation.
Book a Free Call Construction loansTrusted by clients across NSW and Australia-wide
Rated 5.0 from 101 Google reviews. Pulled live from Google, always current.
I had an excellent experience working with LoanBuddy (Shane) mortgage broker. From the beginning, he was professional, knowledgeable...
Read full reviewAbsolutely outstanding service. My mortgage broker Shane was knowledgeable, responsive, and made the entire process smooth and...
Read full reviewWe originally moved to Shane based on a recommendation, and it was one of the best decisions we’ve made. From the start, he’s been...
Read full reviewI’m extremely happy with my experience working with Shane. From the very beginning, they were professional, knowledgeable, and...
Read full reviewReviews from Google. See all reviews for LoanBuddy on Google.